Labour Contract Payment Calculator Pakistan
Labour-only contracts separate workmanship from owner-supplied materials unless expressly included. Confirm whether shuttering, scaffolding, machinery, steel fixing, electrical and plumbing labour are included. Use this free CCG calculator to plan and track your labour contract payments in PKR.
Labour Contract payment planner
Enter cumulative certified gross work, actual receipts and retention releases per stage. Mobilization is included in the schedule; do not enter it twice. Rates and percentages must follow your contract.
| Milestone | % | Scheduled PKR | Certified gross | Retention exempt | Retention held | Released | Received | Outstanding | Remove |
|---|
Planning tool only; not a formal payment certificate. Data is not saved. Negative outstanding means excess receipts. Taxes and advance recovery are outside this planner.
Labour Contract stage-wise payment guide
Labour-only contracts separate workmanship from owner-supplied materials unless expressly included. Confirm whether shuttering, scaffolding, machinery, steel fixing, electrical and plumbing labour are included.
How to calculate your payments
- Enter project and client details.
- Choose area multiplied by agreed rate or a lump sum.
- Enter approved variations and contractual retention.
- Adjust the default milestones to match the signed contract; percentages must total 100%.
- Record cumulative certified amounts, actual receipts and retention releases for each stage.
- Review the outstanding amount and print the report.
Worked example
For 2,850 SFT at an illustrative Rs. 700/SFT, the labour contract is Rs. 1,995,000; the 20% mobilization allocation is Rs. 399,000. These amounts are illustrative, not market rates. The scheduled amount is the revised contract multiplied by the milestone percentage. Certification is based on actual accepted work, not automatically on the planned allocation.
Inspection and payment controls
Before paying for plinth work, verify levels, dimensions and completion of agreed labour. Before slab payments, check reinforcement and shuttering inspection records.
Record approved variations in writing before execution. Retention should follow the contract and be released only when agreed conditions are satisfied. Outstanding certified payment equals gross certified work less retention withheld plus retention released less receipts. Remaining contract cash is not necessarily due today.
Common mistakes to avoid
Do not confuse plot area with covered area, pay twice for mobilization, or assume every milestone is payable before inspection. Keep receipts and signed measurement records. Do not use a payment percentage as a substitute for engineering quality checks.
Frequently asked questions
Who buys cement and steel?
Normally the owner under a labour-only arrangement, subject to the signed scope.
Can I change the percentages?
Yes. The schedule is illustrative and editable. Keep the total at 100%.
Can I save the report?
Use Print / Save PDF. The calculator does not persist entered data.
Is this a formal payment certificate?
No. Taxes, advance recovery and formal certification require separate contractual assessment.