Total Covered Area =
1,125 Sq.ft

S.No Name of Item/Material Quantity Unit Rate Total Cost
1Steel (60 Grade) 1,250 Kgs 265 / Kg RS 331,250
2Fine Aggregate (Sand) 248 Cft 45 / Cft RS 16,120
3Course Aggregate (Crush Stone) 495 Cft 135 / Cft RS 66,825
4Cement (53 Grade) 99 Bags 1,550 / Bag RS 153,450
5Electric Work (Pipes, Boxes etc) 1 Job 35,000 / Job RS 35,000
6Formwork (Shuttering) 1,125 Sq.ft 55 / Sq.ft RS 61,875
7Concrete Mixer with Labour 1 Job 35,000 / Job RS 35,000
8Steel Fixer Charges 1,125 Sq.ft 15 / Sq.ft RS 16,875
9Binding wire & Polythene sheet 1 Job 7,500 / Job RS 7,500
Total Cost of Major Material = RS 723,895